Receive a presentation on the progress of the Fairground Channel project and other infrastructure projects funded with American Rescue Plan Act funds
body
Published Notice Required? Yes ____ No __X__
Public Hearing Required? Yes ____ No __X__
DEPARTMENTAL RECOMMENDATION:
The County Administrator's Office recommends the Solano County Board of Supervisors receive a presentation on the progress of the Fairground Channel project and other infrastructure projects funded with American Rescue Plan Act funds.
SUMMARY/ DISCUSSION:
On April 26, 2022, the Board of Supervisors allocated a total of $7,292,500 in ARPA funds for eight infrastructure projects. On October 4, 2022, the Board of Supervisors allocated $303,000 for three additional infrastructure projects.
The Solano360 Specific Plan for the Fairgrounds property in Vallejo includes drainage improvements to provide 100-year storm protection for the proposed multi-use Solano360 project site. Improvements to the Fairgrounds Channel would also reduce flood risk to adjacent properties. Of the original infrastructure allocation of $7,595,500, $5,000,000 was allocated to the Fairgrounds Channel drainage improvement project. Background information and project status for the Fairgrounds Channel is provided in Attachment A.
Work began on the Channel improvement project on October 10, 2022 with environmental surveys, technical studies, design, and permitting agency coordination. The revised project design is being submitted to Vallejo Flood and Wastewater District for review. Based on the current design, a Request for Proposals for channel construction will be initiated in July to allow the execution of construction contracts by September 2024. Site construction could begin in early to mid-2025 once all agency permits are approved and following the rainy season. Construction is estimated to be completed in summer/fall 2026.
Of the remaining ten infrastructure projects, three, the Collinsville P...