Title: Authorize the Director of Resource Management to award and execute a $2,548,505 construction contract with Swierstok Enterprise, Inc. to replace the Rio Vista Corporation Yard garage structure and Benicia Communication storage building; and Authorize the Director of Resource Management to make necessary amendments to the executed contract, with County Counsel concurrence, within budgeted appropriations
District: All
Attachments: 1. A - Agreement with Swierstok
Related files: 24-721
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Authorize the Director of Resource Management to award and execute a $2,548,505 construction contract with Swierstok Enterprise, Inc. to replace the Rio Vista Corporation Yard garage structure and Benicia Communication storage building; and Authorize the Director of Resource Management to make necessary amendments to the executed contract, with County Counsel concurrence, within budgeted appropriations

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of Resource Management recommends that the Board of Supervisors:

1. Authorize the Director of Resource Management to award and execute a $2,548,505 construction contract with Swierstok Enterprise, Inc to replace the Rio Vista Corporation Yard garage structure and Benicia Communication storage building; and

2. Authorize the Director of Resource Management to make necessary amendments to the executed contract, with County Counsel concurrence, within budgeted appropriations.

SUMMARY:

On October 1, 2024 the Solano County Board of Supervisors authorized the Director of Resource Management to solicit bids, award, and execute a construction contract for $2,200,000 for the Rio Vista Corporation Yard Garage and Benicia Communication Tower Project. After solicitation, the lowest responsive and responsible bid, submitted by Swierstok Enterprise, Inc., exceeded the engineer's original estimate by $348,505.00 for the Rio Vista project portion. There was no overage on the Benicia Communication Tower project portion.

FINANCIAL IMPACT:

The $348,505.00 increase over the original project estimate will be paid for by the County Road Fund, with no impact to the General Fund. The costs associated with preparing this agenda item are nominal and absorbed by the Department's FY2024/25 Working Budget.

DISCUSSION:

Rio Vista Corporation Yard Garage / Benicia Communications Storage Building Project ($2,548,505.00)
The Rio V...