File #: 16-815    Version: 1 Name: NOC 1695 H&SS Emergency Generator Replacement Project
Type: Notice of Completion Status: Approved
In control: General Services
On agenda: 10/25/2016 Final action: 10/25/2016
Title: Approve the Notice of Completion for the replacement of the emergency generator at the Health and Social Services building located at 2101 Courage Drive in Fairfield constructed by Western Machinery Electric of Benicia; and Authorize the Clerk of the Board to record the executed Notice of Completion
District: All
Attachments: 1. A - Notice of Completion, 2. B - Summary of Project Funding and Expense, 3. Executed & Recorded Notice, 4. Minute Order
title
Approve the Notice of Completion for the replacement of the emergency generator at the Health and Social Services building located at 2101 Courage Drive in Fairfield constructed by Western Machinery Electric of Benicia; and Authorize the Clerk of the Board to record the executed Notice of Completion

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:
1. Approve the Notice of Completion (Attachment A) for the replacement of the emergency generator at the Health and Social Services located at 2101 Courage Drive in Fairfield, constructed by Western Machinery Electric of Benicia; and

2. Authorize the Clerk of the Board to record the executed Notice of Completion.

SUMMARY:

On February 9, 2016, the Board awarded a construction contract to Western Machinery Electric to replace the emergency generator and related utilities at the Health and Social Services building located at 2101 Courage Drive in Fairfield (Project). During the course of the construction, the quality of work satisfied the requirements of the construction documents and has been deemed code compliant. General Services is requesting that the Board approve the Notice of Completion for the project and authorize the Clerk of the Board to record the document in order to release funds held by the County.

FINANCIAL IMPACT:

The Board previously approved $340,000 in Accumulated Capital Outlay Fund (Budget Unit 1695) to fund the project. The project budget was reduced by $70,000 due to updated cost estimates. Those funds reverted to ACO Contingencies at FY 2015-16 year-end closing. The total amount of construction expenses associated with Western Machinery Electric's agreement is $190,149. The total project cost, including fees and project management, is $253,563. Remaining project funds of $16,437 will be returned to the Accumulated Capit...