File #: 25-644    Version: 1 Name: Follow up Review of ARPA Contract Subrecipient Monitoring Internal Control Review
Type: Report Status: Consent Calendar
In control: Auditor-Controller
On agenda: 8/5/2025 Final action: 8/5/2025
Title: Accept the Auditor-Controller Internal Audit Division's Follow-up to the ARPA Contract Subrecipient Monitoring Internal Control Review
District: All
Attachments: 1. A - ARPA Contract Subrecipient Monitoring Review Follow-up Report

title

Accept the Auditor-Controller Internal Audit Division’s Follow-up to the ARPA Contract Subrecipient Monitoring Internal Control Review

 

body

Published Notice Required?     Yes ____ No _X _  

Public Hearing Required?         Yes ____ No _X _

 

DEPARTMENTAL RECOMMENDATION:

 

The Auditor-Controller’s Office (ACO) recommends the Board of Supervisors accept the Follow-up to the ARPA Contract Subrecipient Monitoring Internal Control Review.

 

SUMMARY/DISCUSSION:

 

The ACO Internal Audit Division conducted an internal control review of ARPA Contract Subrecipient Monitoring which resulted in a report (Report) dated March 14, 2024. The Report identified two deficiencies in internal controls.

 

Pursuant to the Internal Audit Division’s FY2024/25 Audit Plan, the ACO conducted a follow-up to the ARPA Contract Subrecipient Monitoring Internal Control to determine whether the County Administrator’s Office resolved the control deficiencies identified in the prior review.

 

The ACO conducted a follow-up review to determine the progress in resolving the conditions identified in the Report. Based on the test work in this follow-up review both issues were resolved.

 

FINANCIAL IMPACT:

 

The acceptance of the report has no financial impact.

 

ALTERNATIVES:

 

The Board of Supervisors could elect not to accept the report. This alternative is not consistent with sound public policy and is therefore not recommended.

 

OTHER AGENCY INVOLVEMENT:

 

The County Administrator’s Office has reviewed and accepted the report. Management’s responses have been incorporated into the report.

 

CAO RECOMMENDATION:

 

APPROVE DEPARTMENTAL RECOMMENDATION