File #: 18-266    Version: 1 Name: FAA Grant - Fence and Gate Project
Type: Resolution Status: Consent Calendar
In control: General Services
On agenda: 4/24/2018 Final action: 4/24/2018
Title: Approve a resolution authorizing acceptance of a grant offer agreement from the Federal Aviation Administration (FAA) for construction of the Nut Tree Airport Fence and Gate Project for up to $527,000; and Delegate authority to the County Administrator to execute and administer the grant agreement
District: All
Attachments: 1. A - Resolution, 2. B - Fence and Gate Layout Plan, 3. Adopted Resolution, 4. Minute Order
title
Approve a resolution authorizing acceptance of a grant offer agreement from the Federal Aviation Administration (FAA) for construction of the Nut Tree Airport Fence and Gate Project for up to $527,000; and Delegate authority to the County Administrator to execute and administer the grant agreement

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve a resolution authorizing acceptance of a grant offer agreement from the Federal Aviation Administration (FAA) for construction of the Nut Tree Airport Fence and Gate Project for up to $527,000 (Attachment A); and

2. Delegate authority to the County Administrator to execute and administer the grant agreement.

SUMMARY/DISCUSSION:

The Airport Fence and Gate Project is a part of the Airport Capital Improvement Plan (ACIP) identified in the Airport Master Plan and Airport Business Plan. The Project is planned for construction during summer 2018.

The FAA requires that the County execute and return grant agreements within 10 days of receipt. The County expects to receive a grant offer from the FAA to fund the Fence and Gate Project. The recommended Resolution (Attachment A) will allow the County to be prepared to execute the grant agreement once received, which is anticipated in June 2018.

The Fence and Gate Project will involve approximately 6,350 feet of fencing to complete the Airport's fenced perimeter. The project also includes refurbishment of three existing automated drive-thru gates. Current manual access gates used for airport maintenance functions will also be rehabilitated and three additional manual gates will be installed. Attachment B provides an aerial photograph showing the location of fence and gate improvements.

The Nut Tree Airport Advisory Committee reviewed the project during the Committee's October 2017 and February 20...