File #: 18-580    Version: 1 Name: Notice of Completion for RTIF Safety Improvements
Type: Notice of Completion Status: Consent Calendar
In control: Resource Management
On agenda: 8/28/2018 Final action: 8/28/2018
Title: Approve the Notice of Completion for the Regional Transportation Impact Fee (RTIF) Safety Improvement Project 2017 by Chrisp Company for a final cost of $336,216
District: District 4, District 5, District 3
Attachments: 1. A - Notice of Completion, 2. Minute Order, 3. Recorded NOC
title
Approve the Notice of Completion for the Regional Transportation Impact Fee (RTIF) Safety Improvement Project 2017 by Chrisp Company for a final cost of $336,216

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of Resource Management recommends that the Board of Supervisors approve the Notice of Completion for the Regional Transportation Impact Fee (RTIF) Safety Improvement Project 2017 by Chrisp Company for a final cost of $336,216.

SUMMARY/DISCUSSION:

On March 7, 2017 the Board authorized the Department of Resource Management to advertise for bids and to award and execute a contract with the lowest responsible bidder for the RTIF Safety Improvement Project 2017. This project consisted of signing and striping improvements at various locations. These improvements include but are not limited to thermoplastic striping and markings with enhanced wet/night visibility, LED signs, delineators, and low-profile rumble strips. Chrisp Company of Woodland, CA was the lowest responsible bidder at the bid opening held on September 28, 2017. A contract was awarded to Chrisp Company on October 3, 2017 and executed on October 13, 2017. All construction work on the project has been completed as of August 2018 in compliance with the contract plans and specifications.

Approval of the Notice of Completion allows the Department of Resource Management to make the final payment to the contractor.

FINANCIAL IMPACT:

The project was funded with $305,331 in RTIF funds through joint agreement with the Solano Transportation Authority. Solano Irrigation District provided $3,000 in reimbursement on a joint shoulder fix. The Road Fund provided the remainder $27,885 in funds. There is no impact to the General Fund.

ALTERNATIVES:

The Board could choose to not approve the Notice of Completion for the project. This is not recommended, since it would delay the final payment to th...