File #: 18-769    Version: 1 Name: Agreement with Division 5-15, Inc.for Family Justice Center HVAC Replacement
Type: Contract Status: Approved
In control: General Services
On agenda: 11/6/2018 Final action: 11/6/2018
Title: Approve an agreement with Division 5-15, Inc. of Gold River, CA for $147,515 for the Family Justice Center Heating, Ventilation and Air Conditioning (HVAC) Replacement Project at 604 Empire Street, Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget
District: All
Attachments: 1. A - Contract, 2. B - Project Funding & Budget Summary, 3. C - Bidders of Record, 4. Executed Agreement, 5. Minute Order
title
Approve an agreement with Division 5-15, Inc. of Gold River, CA for $147,515 for the Family Justice Center Heating, Ventilation and Air Conditioning (HVAC) Replacement Project at 604 Empire Street, Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve an agreement with Division 5-15, Inc. of Gold River, CA for $147,515 for the Family Justice Center Heating, Ventilation and Air Conditioning (HVAC) Replacement Project at 604 Empire Street, Fairfield; and
2. Authorize the County Administrator or designee to execute the agreement and any amendments within the approved budget.

SUMMARY:

The Department of General Services recommends the Board approve an agreement (Attachment A) for $147,500 with Division 5-15, Inc. as the lowest responsible bidder for the Family Justice Center HVAC Replacement Project (Project) located at 604 Empire Street in Fairfield.

FINANCIAL IMPACT:

The total approved budget for the Project is $315,000. The budget includes the recommended construction contract of $147,515; project management costs of $45,000; engineering and design fees of $36,500; permits and advertisement of $7,000; and contingency of $78,985. The project is financed by the Criminal Justice Facility Temporary Construction Fund (Budget Unit 4131) with funds residing in Accumulated Capital Outlay (Budget Unit 1739). Attachment B provides breakdown of the funding source and estimated project budget for the Project.

The costs associated with preparing the agenda item are nominal and absorbed by the department's FY2018/19 Adopted Budget.

DISCUSSION:

The Project consists of replacement of existing rooftop HVAC units and existing ductwork, and repairing minor exi...