File #: 19-269    Version: 1 Name: Post Office Construction Contract Award
Type: Contract Status: Approved
In control: General Services
On agenda: 4/9/2019 Final action: 4/9/2019
Title: Approve an agreement for $158,500 with Pro-Ex Construction, Inc. of Rancho Cordova for the Post Office Building Improvements Phase II Project for interior and exterior repairs at 600 Kentucky Street, in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget
District: All
Attachments: 1. A - Contract, 2. B - Project Funding and Budget Summary, 3. C - Bidders of Record, 4. Executed Contract, 5. Minute Order
title
Approve an agreement for $158,500 with Pro-Ex Construction, Inc. of Rancho Cordova for the Post Office Building Improvements Phase II Project for interior and exterior repairs at 600 Kentucky Street, in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve an agreement for $158,500 with Pro-Ex Construction, Inc. of Rancho Cordova for the Post Office Building Improvements Phase II Project for interior and exterior repairs at 600 Kentucky Street, in Fairfield; and

2. Authorize the County Administrator or designee to execute the agreement and any amendments within the approved budget.

SUMMARY:

The Department of General Services is recommending the Board of Supervisors approve an agreement (Attachment A) for $158,500 with Pro-Ex Construction, Inc. as the lowest responsible bidder for the Post Office Building Improvements Phase II Project (Project) located at 600 Kentucky Street, in Fairfield.

FINANCIAL IMPACT:

The total approved budget for the Project is $567,428, including the recommended construction contract for $158,500; other construction-related costs of $15,045; project management costs of $41,000; engineering and design fees of $91,349; permits and inspections of $9,000; miscellaneous expenses of $1,000; and project contingency of $95,000 (Attachment B). There is $156,534 in budgeted reserves resulting from all construction bids coming in lower than the architectural cost estimates of $394,603 for the Project. The Project is financed from the Accumulated Capital Outlay Fund, Capital Renewal Fund and General Expenditures.