File #: 19-433    Version: 1 Name: Professional Services Agreement Part 1
Type: Contract Status: Approved
In control: General Services
On agenda: 6/4/2019 Final action: 6/4/2019
Title: Approve 8 three year agreements beginning June 4, 2019 with AluCeron Consulting Group Inc of Vallejo, CSW/Stuber-Stroeh Engineering Group, Inc. of Novato, Dewberry Architects, Inc. of Sacramento, Geocon Consultants, Inc. of Fairfield, Gilbane Building Company of San Jose, LCA Architects, Inc. of Walnut Creek, Stanton Engineering of Sacramento and Vanir Construction Management, Inc. of Sacramento to provide as-needed consulting services to support approved capital improvement projects; and Authorize the County Administrator or designee to execute the agreements and any amendments within the approved project budgets
District: All
Attachments: 1. A - Link to Contracts and RFQ, 2. B - Submitters of Record, 3. AluCeron Consulting Group Executed Contract, 4. CSW Stuber-Stroeh Engineering Group Executed Contract, 5. Dewberry Architects Executed Contract, 6. Geocon Consultants Executed Contract, 7. Gilbane Building Company Executed Contract, 8. LCA Architects Executed Contract, 9. Vanir Construction Management Executed Contract, 10. Stanton Engineering Executed Contract, 11. Minute Order
title
Approve 8 three year agreements beginning June 4, 2019 with AluCeron Consulting Group Inc of Vallejo, CSW/Stuber-Stroeh Engineering Group, Inc. of Novato, Dewberry Architects, Inc. of Sacramento, Geocon Consultants, Inc. of Fairfield, Gilbane Building Company of San Jose, LCA Architects, Inc. of Walnut Creek, Stanton Engineering of Sacramento and Vanir Construction Management, Inc. of Sacramento to provide as-needed consulting services to support approved capital improvement projects; and Authorize the County Administrator or designee to execute the agreements and any amendments within the approved project budgets

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve 8 three year agreements beginning June 4, 2019 with AluCeron Consulting Group Inc of Vallejo, CSW/Stuber-Stroeh Engineering Group, Inc. of Novato, Dewberry Architects, Inc. of Sacramento, Geocon Consultants, Inc. of Fairfield, Gilbane Building Company of San Jose, LCA Architects, Inc. of Walnut Creek, Stanton Engineering of Sacramento and Vanir Construction Management, Inc. of Sacramento to provide as- needed consulting services to support approved capital improvement projects; and

2. Authorize the County Administrator or designee to execute the agreements and any amendments within the approved project budgets.

SUMMARY:

The Department of General Services is recommending the Board of Supervisors approve the agreements as a competitive qualifications-based selection process was conducted in the open marketplace by the Department of General Services that resulted in the selection of AluCeron Consulting Group Inc of Vallejo, CSW/Stuber-Stroeh Engineering Group, Inc. of Novato, Dewberry Architects, Inc. of Sacramento, Geocon Consultants, Inc. of Fairfield, Gilbane Building Company of San Jose, LCA Architects, Inc. of Walnut...