File #: 19-813    Version: 1 Name: Main Jail Security Cameras
Type: Contract Status: Approved
In control: General Services
On agenda: 10/22/2019 Final action: 10/22/2019
Title: Approve an agreement with Johnson Controls, Inc. of San Leandro for $1,319,583 for the Main Jail Security Improvement Project at 500 Union Avenue, in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget
District: All
Attachments: 1. A - Contract, 2. B - Summary of Project Funding and Expense, 3. C - Bidders of Record, 4. Executed Contract, 5. Minute Order
title
Approve an agreement with Johnson Controls, Inc. of San Leandro for $1,319,583 for the Main Jail Security Improvement Project at 500 Union Avenue, in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve an agreement for $1,319,583 with Johnson Controls, Inc. of San Leandro for the Main Jail Security Improvement Project at 500 Union Avenue in Fairfield; and

2. Authorize the County Administrator or designee to execute the agreement and any amendments within the approved budget.

SUMMARY:

The Department of General Services recommends the Board approve an agreement (Attachment A) for $1,319,583 with Johnson Controls, Inc. as the lowest responsible bidder for the Main Jail Security Improvement Project located at 500 Union Avenue in Fairfield.

FINANCIAL IMPACT:

The Board approved a total project budget of $2,955,927 (BU 1664) from a combination of funding sources including: $2,358,000 from General Fund - Capital Renewal Reserve and General Expenditures; $500,000 from Criminal Justice Temporary Construction Fund; $65,000 from Accumulated Capital Outlay Fund and $32,927 transfer from BU 1744 Main Jail WIFI Connectivity Project.

Planned security upgrades are to occur over four phases of work, with the first two phases funded for design and construction to achieve compliance with Federal statute in the shorter term, and the second two phases funded for design only for future improvements. Funded work includes construction (estimated at $1,319,583), project management (estimated at $95,000) and engineering and design fees ($328,648). Total estimated project cost for the first two phases including design only work for future phases is $1,743,231. Attac...