header-left
File #: 20-26    Version: 1 Name: JDF Security System Upgrade
Type: Contract Status: Approved
In control: General Services
On agenda: 1/14/2020 Final action: 1/14/2020
Title: Approve an agreement for $794,000 with Status Electrical Corporation of British Columbia, Canada for the Juvenile Detention Facility Security System Upgrades Project at 740 Beck Avenue in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget
District: All
Attachments: 1. A - Contract, 2. B - Budget Summary, 3. C - Bid Results, 4. Executed Contract, 5. Minute Order
title
Approve an agreement for $794,000 with Status Electrical Corporation of British Columbia, Canada for the Juvenile Detention Facility Security System Upgrades Project at 740 Beck Avenue in Fairfield; and Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget

body
Published Notice Required? Yes ____ No _X _
Public Hearing Required? Yes ____ No _X _

DEPARTMENTAL RECOMMENDATION:

The Department of General Services recommends that the Board of Supervisors:

1. Approve an agreement for $794,000 with Status Electrical Corporation of British Columbia, Canada for the Juvenile Detention Facility Security System Upgrades Project at 740 Beck Avenue in Fairfield; and

2. Authorize the County Administrator or designee to execute the agreement and any amendments within the approved project budget.

SUMMARY:

The Department of General Services is recommending the Board of Supervisors approve an agreement (Attachment A) for $794,000 with Status Electrical Corporation as the lowest responsible bidder for the Juvenile Detention Facility Security System Upgrades Project at 740 Beck Avenue, in Fairfield.

FINANCIAL IMPACT:

The total approved project budget for the Juvenile Detention Facility Security System Upgrades (Project) is $1,825,000 (Budget Unit 1749) which includes the recommended construction contract for $794,000; project management costs for $270,000; engineering and design fees for $120,000; permits and inspections for $12,000; miscellaneous expenses (Advertising, Prints, Mailing, etc.) for $13,000; and project contingencies of $616,000. The project is funded from FY15/16 BU#1740 New Foundations Improvements Project Savings of $97,764; AB109 Fund of $450,885; Accumulated Capital Outlay Fund of $1,351; and General Fund State Mandated Cost of $1,275,000. Attachment B provides breakdown of the estimated project cost and funding sources for the Project. The costs associated with ...